| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 280.2.003 | PLACA DE MARMOL SANTO TOMAS COLOR ARANDA LILA GRIS DE 2 CMS DE ESPESOR CON ZOCLO AL FONDO Y UN LATERAL DE 10 CMS Y FALDON DE 12 CMS AL FRENTE Y UN LATERAL, ARISTAS BOLEADAS EN SANITARIOS EMPLEADOS DE 2.09 X 0.60 CON 3 HUECOS PARA OVALIN | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MR-01 | MARMOL EN PLACAS | M2 | 1.250000 | $3,000.00 | $3,750.00 |
| ZOCLO Y FALDON | ZOCLO Y FALDON | PZA | 1.000000 | $1,800.00 | $1,800.00 |
| DISCO DE DIAMANTE | DISCO DE DIAMANTE | PZA | 0.001670 | $1,460.72 | $2.44 |
| ACABOL | BOLEADO DE ARISTAS | ML | 3.500000 | $207.33 | $725.66 |
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.030000 | $0.00 | $0.00 |
| Suma de Material | $6,278.09 | ||||
| Mano de Obra | |||||
| CUAD OC 65 | CUAD. 1 AZULEJERO + 1 AYTE. DE AZULEJERO | jor | 0.208750 | $592.82 | $123.75 |
| Suma de Mano de Obra | $123.75 | ||||
| Equipo | |||||
| ESMERILADORA | Esmeriladora | HR | 0.083500 | $9.24 | $0.77 |
| Suma de Equipo | $0.77 | ||||
| Auxiliar | |||||
| LECHADA CEMENTO BLAN | LECHADA CEMENTO BLANCO-AGUA | M3 | 0.006680 | $2,787.70 | $18.62 |
| ACARRE40M | ACARREO HORIZONTAL SIN PENDIENTE. EN CARRETILLA DE 3.5 FT3, A 40.00 M. INCLUYE CARGA Y DESCARGA DEL MATERIAL | M3 | 0.050100 | $35.89 | $1.80 |
| MORTERO CEM-ARE 1:4 | Mortero cemento arena 1 : 4 | M3 | 0.045090 | $815.25 | $36.76 |
| Suma de Auxiliar | $57.18 | ||||
| Costo Directo | $6,459.80 |