| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2703-006 | MURO DE CONCRETO ARMADO EN ZONA DE BAÑOS DE 11 CM DE ESPESOR F C= 200 KG/CM2 ARMADO CON VARILLA DEL NO. 3 @ 15 CM AMBOS LECHOS SENTIDOS , INCLUYE: MATERIALES, EQUIPO, HERRAMIENTA Y MANO DE OBRA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC.PREMEZ.FC=200 | CONCRETO PREMEZCLADO F'C= 200 KG/CM2 | M3 | 0.115500 | $860.00 | $99.33 |
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 8.187900 | $7.00 | $57.32 |
| CIMBRAPLAY 16 MM | CIMBRAPLAY 16MM | M2 | 2.200000 | $95.00 | $209.00 |
| CLAVO (VARIAS MED.) | CLAVO PARA MADERA VARIAS MEDIDAS | KG | 0.166200 | $13.75 | $2.29 |
| DESMOLDANTE | DESMOLDANTE | LT | 0.500000 | $7.00 | $3.50 |
| CHAFLAN 1" | CHAFLAN 1" | Ml | 1.000000 | $3.20 | $3.20 |
| MADERA DE PINO | MADERA DE PINO | PT | 5.200000 | $4.50 | $23.40 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.290390 | $14.00 | $4.07 |
| Suma de Material | $402.10 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 16 | (1 Of. Carpintero + 1Ayudante) | jor | 0.090000 | $649.65 | $58.47 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.250000 | $592.82 | $148.21 |
| CUAD OC 62 | CUAD. 1 FIERRERO + 1 AYUDANTE DE FIERRERO | jor | 0.054377 | $592.82 | $32.24 |
| Suma de Mano de Obra | $238.91 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR. | HERRAMIENTA MENOR | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $641.01 |