| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 27011-026 | SUMINISTRO Y FABRICACION DE PASO EN MURO PARA TUBERIAS DE REFRIGERACION DE SECCION 3.02 X 0.61 MTS ARMADO CON VARILLA SEGUN PROYECTO, INCLUYE: MATERIALES, EQUIPO, HERRAMIENTA Y MANO DE OBRA | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 17.300000 | $7.00 | $121.10 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.950000 | $14.00 | $13.30 |
| ACE#4 | ACERO DE REFUERZO De 1/2" #4 f`y = 4200 kg/ml | kg | 30.270000 | $7.00 | $211.89 |
| Suma de Material | $346.29 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.600000 | $592.82 | $355.69 |
| Suma de Mano de Obra | $355.69 | ||||
| Auxiliar | |||||
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.319000 | $851.14 | $271.51 |
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Auxiliar | $271.51 | ||||
| Concepto | |||||
| 305 | SUMINISTRO Y HABILITADO DE CIMBRA APARENTE EN TRABES, Y CORNIZAS A BASE DE TRIPLAY DE PINO DE 16MM DE ESPESOR EN ESTRUCTURA (MAXIMO 4 USOS), INCLUYE OBRA FALSA, CHAFLANES, CONSUMIBLES, DESENCOFRANTE Y DESCIMBRA DE LOS ELEMENTOS, TODOS LOS MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO, ACARREOS HORIZONTALES Y VERTICALES, DESPERDICIOS Y TODO AQUELLO NECESARIO PARA LA CORRECTA Y COMPLETA EJECUCION DE ESTE CONCEPTO, INCLUYE ADEMAS LIMPIEZA DE OBRA Y RETIRO DE SOBRANTES FUERA DE LA OBRA. (P.U.O.T.) | M2 | 2.900000 | $126.74 | $367.55 |
| Suma de Concepto | $367.55 | ||||
| Costo Directo | $1,341.04 |