| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 270.11.014 | SARDINEL DE CONCRETO F'C=150 KG/CM2 DE 10 X 10 ANCLADO CON 1 VAR No. 3 @ 30 CMS DE 20 CMS FORRADO CON LOSETA CERAMICA INTERCERAMIC METALIC ALUMINIUM 30 X 30 | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 0.445600 | $7.00 | $3.12 |
| LOSETA META | LOSETA METALIC | M2 | 0.315000 | $120.00 | $37.80 |
| Suma de Material | $40.92 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.250000 | $592.82 | $148.21 |
| Suma de Mano de Obra | $148.21 | ||||
| Auxiliar | |||||
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3 | 0.010500 | $782.02 | $8.21 |
| Suma de Auxiliar | $8.21 | ||||
| Costo Directo | $197.34 |