| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 5407-0016 | SUMINISTRO Y FABRICACION DE DALA DE REMATE EN MURO DE BLOCK DE SECCION 15 X 20 CM F C=200 KG/CM2 ARMADO CON 4 VAR. DEL NO. 3 Y ESTR. DEL NO. 2 @ 20 CM CON ARISTAS CON CAFLAN A 45 , INCLUYE: MATERIALES, EQUIPO, HERRAMIENTA Y MANO DE OBRA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC.PREMEZ.F-C=200 | Concreto Premezclado F'c=200 Kg/cm2AM 3/4" REV. 10 cm +- 2.5 cm | M3 | 0.031500 | $1,000.00 | $31.50 |
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 2.500000 | $7.00 | $17.50 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.130900 | $14.00 | $1.83 |
| ACE#4 | ACERO DE REFUERZO De 1/2" #4 f`y = 4200 kg/ml | kg | 4.170000 | $7.00 | $29.19 |
| Suma de Material | $80.02 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.125000 | $592.82 | $74.10 |
| Suma de Mano de Obra | $74.10 | ||||
| Auxiliar | |||||
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Auxiliar | $0.00 | ||||
| Concepto | |||||
| 305 | SUMINISTRO Y HABILITADO DE CIMBRA APARENTE EN TRABES, Y CORNIZAS A BASE DE TRIPLAY DE PINO DE 16MM DE ESPESOR EN ESTRUCTURA (MAXIMO 4 USOS), INCLUYE OBRA FALSA, CHAFLANES, CONSUMIBLES, DESENCOFRANTE Y DESCIMBRA DE LOS ELEMENTOS, TODOS LOS MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO, ACARREOS HORIZONTALES Y VERTICALES, DESPERDICIOS Y TODO AQUELLO NECESARIO PARA LA CORRECTA Y COMPLETA EJECUCION DE ESTE CONCEPTO, INCLUYE ADEMAS LIMPIEZA DE OBRA Y RETIRO DE SOBRANTES FUERA DE LA OBRA. (P.U.O.T.) | M2 | 0.800000 | $126.74 | $101.39 |
| Suma de Concepto | $101.39 | ||||
| Costo Directo | $255.52 |