| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2702-001 | DALA DE CERRAMIENTO EN FAST FOOD F C= 250 KG/CM2 DE SECCION 0.50 X 0.20 MTS ARMADA CON 6 VAR. DEL NO. 4 Y ESTR. DEL NO. 3 @ 20 CM, INCLUYE: CIMBRA DESCIMBRA, EQUIPO, HERRAMIENTA Y MANO DE OBRA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.440600 | $14.00 | $6.17 |
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 4.910000 | $7.00 | $34.37 |
| ACE#4 | ACERO DE REFUERZO De 1/2" #4 f`y = 4200 kg/ml | kg | 6.270000 | $7.00 | $43.89 |
| Suma de Material | $84.43 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.083333 | $592.82 | $49.40 |
| Suma de Mano de Obra | $49.40 | ||||
| Auxiliar | |||||
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.105000 | $851.14 | $89.37 |
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Auxiliar | $89.37 | ||||
| Concepto | |||||
| 305 | SUMINISTRO Y HABILITADO DE CIMBRA APARENTE EN TRABES, Y CORNIZAS A BASE DE TRIPLAY DE PINO DE 16MM DE ESPESOR EN ESTRUCTURA (MAXIMO 4 USOS), INCLUYE OBRA FALSA, CHAFLANES, CONSUMIBLES, DESENCOFRANTE Y DESCIMBRA DE LOS ELEMENTOS, TODOS LOS MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO, ACARREOS HORIZONTALES Y VERTICALES, DESPERDICIOS Y TODO AQUELLO NECESARIO PARA LA CORRECTA Y COMPLETA EJECUCION DE ESTE CONCEPTO, INCLUYE ADEMAS LIMPIEZA DE OBRA Y RETIRO DE SOBRANTES FUERA DE LA OBRA. (P.U.O.T.) | M2 | 1.000000 | $126.74 | $126.74 |
| Suma de Concepto | $126.74 | ||||
| Costo Directo | $349.94 |