| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| L16 | SUM. E INST. DE CAJA CONDULET LB, LR, LL 16 MM | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONDULET 13 OVAL. | CONDULET 13 OVAL. | PZA | 1.000000 | $52.00 | $52.00 |
| CONDULET 13 OVAL. | CONDULET 13 OVAL. | PZA | 1.000000 | $52.00 | $52.00 |
| CONDULET 13 OVAL. | CONDULET 13 OVAL. | PZA | 1.000000 | $52.00 | $52.00 |
| CONDULET 13 OVAL. | CONDULET 13 OVAL. | PZA | 1.000000 | $52.00 | $52.00 |
| Suma de Material | $208.00 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.049860 | $775.62 | $38.67 |
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.049860 | $775.62 | $38.67 |
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.049860 | $775.62 | $38.67 |
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.049860 | $775.62 | $38.67 |
| Suma de Mano de Obra | $154.69 | ||||
| Costo Directo | $362.69 |