| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IE-03A-05 | TUBO C.G.P.G.25 MM | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO C.G.P.G. 27 MM | TUBO C.G.P.G. 27 MM | PZA | 1.030000 | $52.60 | $54.18 |
| SOPORTE P/TUBERIA | SOPORTE P/TUBERIA | PZA | 0.200000 | $32.00 | $6.40 |
| MATER. MISCELANEOS | MATER. MISCELANEOS | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Material | $60.58 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENS | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.041670 | $715.38 | $29.81 |
| Suma de Mano de Obra | $29.81 | ||||
| Costo Directo | $90.39 |