| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HD-32 | SOPORTERIA PARA INSTALACION DE TUBERIAS HIDRAULICAS Y SANITARIAS | LOTE |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ABRAZ-PERA 100 MM | ABRAZ-PERA 100 MM | PZA | 56.000000 | $16.50 | $924.00 |
| MORDAZA | MORDAZA | PZA | 56.000000 | $45.00 | $2,520.00 |
| VARILLA ROSC. 3/8 | VARILLA ROSC. 3/8 | ML | 85.000000 | $15.75 | $1,338.75 |
| TUERCA GALV. 3/8" | TUERCA GALV. 3/8" | PZA | 150.000000 | $0.29 | $43.50 |
| Suma de Material | $4,826.25 | ||||
| Mano de Obra | |||||
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 14.200000 | $723.79 | $10,277.82 |
| Suma de Mano de Obra | $10,277.82 | ||||
| Costo Directo | $15,104.07 |