| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IE-04-24 | SOPORTERIA PARA CONTACTO Y FUERZA | LOTE |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ABRZADER13 | ABRAZADERA DE UÑA DE 13 MM | PZA | 150.000000 | $9.50 | $1,425.00 |
| TUERCA GALV. 3/8" | TUERCA GALV. 3/8" | PZA | 1,200.000000 | $0.29 | $348.00 |
| VARILLA ROSC. 3/8 | VARILLA ROSC. 3/8 | ML | 100.000000 | $15.75 | $1,575.00 |
| CINTA PERFORADA CLEV | CINTA PERFORADA CLEV | ML | 300.000000 | $5.50 | $1,650.00 |
| ANGULO FO.11/4X1/4" | ANGULO FO.11/4X1/4" | KG | 150.000000 | $7.50 | $1,125.00 |
| UNICANAL U-10 | UNICANAL U-10 | ML | 10.000000 | $12.35 | $123.50 |
| PERNO P/CONCRETO | PERNO Y FULMINANTE | JGO | 150.000000 | $7.00 | $1,050.00 |
| MATER. MISCELANEOS | MATER. MISCELANEOS | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Material | $7,296.50 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENS | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 2.000000 | $715.38 | $1,430.76 |
| CUADRILLA BAJA TENS | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 2.000000 | $715.38 | $1,430.76 |
| Suma de Mano de Obra | $2,861.52 | ||||
| Costo Directo | $10,158.02 |