| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| SOPM01 | SOPORTE TIPO CAMA, A BASE DE UNICANAL Y ABRAZADERAS UNICANAL CON UNA LONG. HASTA DE 1.30 M. DEL COLGANTE, ASIENTO DE GOMA, INCLUYE: SUMINISTRO, BARRENOS, TAQUETES DE EXPANSION, SOLDADURA, TUERCAS, ROLDANAS, TRAZO,COLOCACION, PINTURA, HERRAMIENTAS Y EQUIPO EN CUALQUIER NIVEL. PARA 1 TUBO | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| UNICANAL U-10 | UNICANAL U-10 | ML | 0.118420 | $12.35 | $1.46 |
| ASIENTO GOMA | ASIENTO GOMA | PZA | 1.000000 | $16.25 | $16.25 |
| VARILLA ROSCADA 1/4" | VARILLA ROSCADA DE 1/4" TRAMO DE 3 MTS | ML | 1.111110 | $7.25 | $8.06 |
| TUERCA GALV. 1/4" | TUERCA GALV. 1/4" | PZA | 2.000000 | $0.15 | $0.30 |
| ROLDANA DE 1/4" | ROLDANA DE 1/4" | PZA | 2.000000 | $0.10 | $0.20 |
| ABRAZ UNICANAL 51 MM | ABRAZADERA UNICANAL 51 MM | PZA | 1.000000 | $9.26 | $9.26 |
| Suma de Material | $35.53 | ||||
| Mano de Obra | |||||
| CUAD INST ESPECIAL | CUADRILLA DE INSTALACIONES ESPECIALES | jor | 0.032000 | $951.92 | $30.46 |
| Suma de Mano de Obra | $30.46 | ||||
| Costo Directo | $65.99 |