| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IE-06-23 | TUBO C.G.P.G. 38 MM | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO C.G.P.G. 40MM | TUBO C.G.P.G. 40MM | PZA | 1.030000 | $92.00 | $94.76 |
| SOPORTE P/TUBERIA | SOPORTE P/TUBERIA | PZA | 0.250000 | $32.00 | $8.00 |
| MATER. MISCELANEOS | MATER. MISCELANEOS | (%)mo | 0.050000 | $0.00 | $0.00 |
| SEGUETA | SEGUETA | PZA | 0.050000 | $7.00 | $0.35 |
| GUIA ALAMBRE 12 | ALAMBRE PARA GUIA | ML | 1.010000 | $1.66 | $1.68 |
| Suma de Material | $104.79 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENS | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.062500 | $715.38 | $44.71 |
| Suma de Mano de Obra | $44.71 | ||||
| Auxiliar | |||||
| ANDAMIO | MODULO DE 1.55 MTS PARA INSTALACIONES | R/D | 0.066670 | $31.32 | $2.09 |
| Suma de Auxiliar | $2.09 | ||||
| Costo Directo | $151.59 |