| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EQUIP-02 | COLOCACION DE VENTILADOR EN TECHUMBRE, INCLUYE: CHASIS DE LAMINA EN CALIBRE 20, EMPAQUES DE NEOPRENO, PIJAS DE 1/4" X 7/8", SELLADOR, ELEVACION, MANIOBRAS, COLOCACION, FIJACION, EQUIPO, M.O., MATERIALES MISCELANEOS, (NO INCLUYE REFUERZO DE TECHUMBRE) | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TAQUETE SCI 3/8" | TAQUETE SCI 3/8" | PZA | 9.000000 | $6.60 | $59.40 |
| TORNILLO 3/8X1 1/2 | CON TUERCA Y ARANDELA | PZA | 9.000000 | $3.30 | $29.70 |
| TUERCA GALV. 3/8" | TUERCA GALV. 3/8" | PZA | 9.000000 | $0.29 | $2.61 |
| ANGULO 1 1/2" X 1/4" | ANGULO 1 1/2" X 1/4" | KG | 12.300000 | $7.50 | $92.25 |
| SOLDADURA E7018 | SOLDADURA E7018 | KG | 1.000000 | $35.00 | $35.00 |
| CHASIS DE LAMINA | CHASIS DE LAMINA CAL. 18 | PZA | 0.800000 | $3,055.52 | $2,444.42 |
| NEOPRENO 3/4" | NEOPRENO 3/4" | KG | 13.000000 | $12.30 | $159.90 |
| PIJAS 1/4" X 7/8" | PIJAS 1/4" X 7/8" | PZA | 12.000000 | $2.30 | $27.60 |
| SELLADOR PLAST | SELLADOR PLASTICEMEN | LT | 1.800000 | $65.00 | $117.00 |
| Suma de Material | $2,967.88 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 18 | Cuadrilla No. 18 ( 1 Of. Fierrero + 1Ayudante). | jor | 0.800000 | $513.17 | $410.54 |
| CUADRILLA BAJA TENS | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 1.100000 | $715.38 | $786.92 |
| CUADRILLA A.A. | AIRE ACONDICIONADO | jor | 2.500000 | $1,098.82 | $2,747.05 |
| CUAD MANIOBR INST | CUAD MANIOBR INST | jor | 1.500000 | $1,249.21 | $1,873.82 |
| Suma de Mano de Obra | $5,818.32 | ||||
| Equipo | |||||
| SOLDADORA EST. | Soldadora Miller Dimension Mod. 652 | HR | 0.500000 | $31.60 | $15.80 |
| GRUAS P | 20 TON. COMPLETA | HR | 2.000000 | $452.21 | $904.42 |
| GRUA HIAB | Grua Tipo Hiab de 3.5 ton.Montada en camion de 10 ton | HR | 1.500000 | $373.60 | $560.40 |
| Suma de Equipo | $1,480.62 | ||||
| Costo Directo | $10,266.82 |