| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| TRAMPA01 | TRAMPA DE GRASAS DE CONCRETO ARMADO SEGUN PROYECTO INCLUYE: EXCAVACION, CIMBRA, DECIMBRA, RELLENO, MANO DE OBRA, MATERIALES, HERRAMIENTA Y EQUIPO. 1.0x1.0x1.50 | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | M3 | 0.100000 | $40.00 | $4.00 |
| MAMP-GALV | MAMPARA DE LAMINA GALVANIZADA DE CAL.14 1.00x0.70 COMO DIVISION | PZA | 1.000000 | $180.00 | $180.00 |
| ACE#3 A #8 | ACERO DE REFUERZO DE 3/8" #3 HASTA #8 f`y = 4200 kg/ml | KG | 177.000000 | $8.69 | $1,538.13 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 4.250000 | $10.12 | $43.01 |
| CIMBRAPLAY 16 MM. | cimbraplay de contacto de 16 mm. | M2 | 3.050000 | $65.00 | $198.25 |
| DUELA ECONOMICA 3/4" | Duela Economica 3/4" x 3 1/2" x 8 1/4' | pt | 60.000000 | $6.20 | $372.00 |
| CLAVO CON CABEZA DE | Clavo con cabeza de 3" .004KG/PZA PROM. | kg | 3.500000 | $16.12 | $56.42 |
| DIESEL | diesel | Lt | 12.000000 | $5.50 | $66.00 |
| CHAFLAN DE MADERA DE | CHAFLAN DE MADERA DE PINO DE 3A. DE 1" | M | 15.500000 | $3.00 | $46.50 |
| Suma de Material | $2,504.31 | ||||
| Mano de Obra | |||||
| CUADRILLA-SAMS-05 | 1 ALBAÑIL + 1 PEON | JOR | 1.500000 | $617.54 | $926.31 |
| CUADRILLA-SAMS-06 | 1 OFICIAL CARPINTERO + 1 AYUDANTE | JOR | 2.500000 | $676.96 | $1,692.40 |
| Suma de Mano de Obra | $2,618.71 | ||||
| Equipo | |||||
| VIBRADOR P/CONCRETO | Vibrador para concreto Mot. Kohler 4 H.Con operador. | HR | 1.850000 | $80.65 | $149.20 |
| Suma de Equipo | $149.20 | ||||
| Auxiliar | |||||
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra, resistencia normal, T.M.A. 3/4" | M3 | 1.300000 | $601.26 | $781.64 |
| Suma de Auxiliar | $781.64 | ||||
| Costo Directo | $6,053.86 |