| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ESCAP-01 | FABRICACION E INSTALACION DE ESCAPE ATMOSFERICO , INCLUYE: LAMINA EN CALIBRE 14, DE MEDIDAS DE CORTE PLUMA, MEDICION, TRAZO, CORTE,ROLADO, DESPERDICIOS, NIVELACION, SOLDADURA,ESMERILADORA, PINTURA, FLETEA OBRA, LIJADO, COLOCACION, FIJACION, LIMPIEZA Y RETIRO DE SOBRANTES FUERA DE LA OBRA, EQUIPO DE SEGURIDAD, INSTALACIONES ESPECIFICAS. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| LAMINA CAL. 14 | LAMINA CAL. 14 | KG | 115.000000 | $16.00 | $1,840.00 |
| SOLDADURA E7018 | SOLDADURA E7018 | KG | 2.000000 | $35.00 | $70.00 |
| PINTURA SHERWIN | PINTURA SHERWIN | LT | 5.200000 | $51.40 | $267.28 |
| ESTOPA | ESTOPA | KG | 0.300000 | $13.20 | $3.96 |
| PINTURA PRIMARIO | PINTURA PRIMARIO | LT | 2.700000 | $45.00 | $121.50 |
| THINNER | THINNER | LT | 1.200000 | $14.00 | $16.80 |
| Suma de Material | $2,319.54 | ||||
| Mano de Obra | |||||
| CUADRILLA A.A. | AIRE ACONDICIONADO | jor | 1.000000 | $1,098.82 | $1,098.82 |
| CUADRILLA SOLDADOR | 1 of.soldador + 1 ayudante E. | jor | 1.000000 | $532.49 | $532.49 |
| CUADR INST PINTURA | (Pintura en tuberias tanques y equipos) | jor | 1.000000 | $699.42 | $699.42 |
| CUADRILLA NO. 02 INS | (2 peones inst.,resanes, excavaciones, acarreos). | jor | 1.250000 | $312.38 | $390.48 |
| Suma de Mano de Obra | $2,721.21 | ||||
| Equipo | |||||
| SOLDADORA EST. | Soldadora Miller Dimension Mod. 652 | HR | 2.750000 | $31.60 | $86.90 |
| ESMERILADORA | Esmeriladora | HR | 1.200000 | $8.24 | $9.89 |
| DOBLADORA P/LAMINA | DOBLADORA PARA LAMINA | jor | 3.000000 | $84.38 | $253.14 |
| Suma de Equipo | $349.93 | ||||
| Costo Directo | $5,390.67 |