| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IE-02-26 | TUBO C.G.P.G.13 MM | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO C.G.P.G. 16MM | TUBO C.G.P.G. 13MM | PZA | 1.030000 | $39.78 | $40.97 |
| SOPORTE P/TUBERIA | SOPORTE P/TUBERIA | PZA | 0.200000 | $32.00 | $6.40 |
| MATER. MISCELANEOS | MATER. MISCELANEOS | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Material | $47.37 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENS | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.033330 | $715.38 | $23.84 |
| Suma de Mano de Obra | $23.84 | ||||
| Costo Directo | $71.22 |