| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| TRINC | TRINCHERA DE 2.50x0.50x35 PARA DESCARGA DE B.A.P. DE Fo.Fo. FORJADO A BASE DE CONCRETO ARMADO DE F'C=200 KG/CM2, CON VARILLA DEL No.3, INCLUYE TAPA CON MARCO Y CONTRAMARCO, MATERIALES, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | PZA* |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| REJILLA IRVING | REJILLA IRVING | KG | 55.000000 | $25.00 | $1,375.00 |
| MARCO CONTRAMARCO 02 | De angulo de 11/2"x1/4" y 1 1/4"X1/4" para registro | PZA | 1.000000 | $550.00 | $550.00 |
| ACE#3 A #8 | ACERO DE REFUERZO DE 3/8" #3 HASTA #8 f`y = 4200 kg/ml | KG | 10.350000 | $8.69 | $89.94 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.003150 | $10.12 | $0.03 |
| POLÍN 3 1/2 X 3 1/2" | Polín 3 1/2 x 3 1/2" x 8 1/4' | pt | 1.000000 | $5.00 | $5.00 |
| CONC.PREMEZ.F-C=200 | Concreto Premezclado F'c=200 Kg/cm2AM 3/4" REV. 10 cm +- 2.5 cm | M3 | 0.350000 | $782.00 | $273.70 |
| CIMBRAPLAY 16 MM. | cimbraplay de contacto de 16 mm. | M2 | 1.160000 | $65.00 | $75.40 |
| AGUA | AGUA | M3 | 0.050000 | $40.00 | $2.00 |
| Suma de Material | $2,371.07 | ||||
| Mano de Obra | |||||
| CUADRILLA-SAMS-05 | 1 ALBAÑIL + 1 PEON | JOR | 0.100000 | $617.54 | $61.75 |
| Suma de Mano de Obra | $61.75 | ||||
| Concepto | |||||
| DRES-0008. | EXCAVACION A MANO EN MATERIAL TIPO II, EN SECO HASTA 2.00 M., DE PROF. PARA ALOJAR TUBERIA, INCLUYE AFINE DE TALUDES Y ABUNDAMIENTO | M3 | 1.000000 | $72.88 | $72.88 |
| RELL-EXC * | RELLENO TENDIDO Y COMPACTADO AL 95% PVSM CON MATERIAL PRODUCTO DE LA EXCAVACION COLOCADO EN CAPAS NO MAYORES DE 20 CMS. DE ESPESOR. | M3 | 0.500000 | $89.44 | $44.72 |
| Suma de Concepto | $117.60 | ||||
| Costo Directo | $2,550.43 |