| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | | | | |
| MARCO CONTRAMARCO M. | De angulo 1 1/2" x 1/4" y 1 1/4"x1/4". PARA REGISTRO. | Pza | 1.000000 | $350.00 | $350.00 |
| DUELA ECONOMICA 3/4" | Duela Economica 3/4" x 3 1/2" x 8 1/4' | pt | 0.690000 | $6.20 | $4.28 |
| GRAVA DE 3/4" 19 MM. | Grava de 3/4" 19 mm. TRITURADA | m3 | 0.032000 | $130.00 | $4.16 |
| Suma de Material | | | | $358.44 |
| Mano de Obra | | | | |
| CUADRILLA-SAMS-05 | 1 ALBAÑIL + 1 PEON | JOR | 0.350000 | $617.54 | $216.14 |
| Suma de Mano de Obra | | | | $216.14 |
| Auxiliar | | | | |
| EXCAVA-MAN | EXCAVACION POR MEDIO MANUAL EN CEPAS, EN MATERIAL CLASE A, MEDIDO EN BANCO, INCLUYE:MATERIALES MANO DE OBRA Y HERRAMIENTA | M3. | 0.600000 | $116.61 | $69.97 |
| PLANT-5CM | PLANTILLA DE CONCRETO, CON AGREGADO MAXIMO DE40 MM., INCLUYE: TRAZO, FRONTERAS, NIVELADO, HUME-DECIDO DE LA SUPERFICIE DE TERRENO, APIZONADO, CO-LADO, CURADO, DESPERDICIOS, EQUIPO, HERRAMIENTA,MANO DE OBRA, LIMPIEZA DEL AREA Y RETIRO DE SO-BRANTES FUERA DE LA OBRA, EQUIPO DE SEGURIDAD, INSTALACIONES ESPECIFICAS, DEPRECIACION Y DEMASDERIVADOS DEL USO DE HERRAMIENTA Y EQUIPO.DE 0.05 M., DE ESPESOR, DE F'c=100 KG/CM2., | M2. | 0.630000 | $63.94 | $40.28 |
| MUR-TAB | MURO DE TABIQUE DE BARRO ROJO RECOCIDO ASENTADOCON MORTERO, INCLUYE: CARGO DIRECTO POR EL COSTO DE LOS MATERIALES Y MANO DE OBRA QUE INTERVEN-GAN, FLETE A OBRA, DESPERDICIO, ACARREO HASTA ELLUGAR DE SU UTILIZACION, HUMEDECIDO, CORTE, AJUSTE,ELABORACION DEL MORTERO, MOCHETA, ENRASE, PRUE-BAS, LIMPIEZA Y RETIRO DE SOBRANTES FUERA DE OBRA,EQUIPO DE SEGURIDAD, INSTALACIONES ESPECIFICAS, DE-PRECIACION Y DEMAS DERIVADOS DEL USO DE HERRA-MIENTA Y EQUIPO, EN CUALQUIER NIVEL.DE 14 CM. DE ESPESOR, ACABADO COMUN, CEMENTO-ARENA-CAL 1:3.5:0.25. | M2. | 1.800000 | $184.79 | $332.62 |
| BAS-APLANA | APLANADO FINO EN MUROS A CUALQUIER NIVEL A PLOMO Y REGLA CON MORTERO CEMENTO-ARENA 1:5 ESPESOR PROMEDIO = 2 CM. INCLUYE REPELADO PULIDO CON PLANA, FABRICACIÓN DE MORTERO Y TODOS LOS MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO, ACARREOS,. INCLUYE ADEMÁS LIMPIEZA DEL ÁREA Y RETIRO DE SOBRANTES FUERA DE LA OBRA. | M2 | 1.800000 | $68.00 | $122.40 |
| CADENA 15 X 15 | CADENA 15 X 15 | ML | 2.000000 | $166.28 | $332.56 |
| Suma de Auxiliar | | | | $897.83 |
| Concepto | | | | |
| RELLENO-06 | SUMINISTRO, TENDIDO Y COMPACTADO AL 90% DE MATERIAL DE PRODUCTO DE EXCAVACION PARA COMPLEMENTAR CEPAS | M3 | 0.500000 | $124.80 | $62.40 |
| 408 | FIRME DE CONCRETO ARMADO DE 12cm DE ESPESOR ACABADO RUSTICO PARA RECIBIR LOSETA CERÁMICA A BASE DE CONCRETO PREMEZCLADO BOMBEADO F'C=250 KG/CM2 AGREGADO MÁXIMO 3/4" R.N., PARRILLA DE VARILLA DEL No. 3 EN EL LECHO SUPERIOR A CADA 24cm AMBOS SENTIDOS, INCLUYE PRUEBAS DE LABORATORIO, CIMBRA EN FRONTERAS, VIBRADO, CURADO, Y TODOS LOS MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO, FABRICACIÓN, ACARREOS INTERNOS NECESARIOS PARA LA COMPLETA Y CORRECTA EJECUCIÓN DE ESTE CONCEPTO, LIMPIEZA Y RETIRO DE SOBRANTES FUERA DE LA OBRA. (P.U.O.T.) | M2 | 0.400000 | $186.41 | $74.56 |
| Suma de Concepto | | | | $136.96 |
| Costo Directo | | | | $1,609.37 |