| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PISO01 * | PISO DE CONCRETO DE 22 CMS DE ESPESOR A BASE DE CONCRETO PREMEZCLADO CON MUDULO DE RUPTURA DE 40, INCLUYE MICROFIBRA DE POLIPROPILENO,DE ACUERDO A NORMA ASTM C 1116 A RAZON DE 600 GRAMOS/1 M3 DE CONCRETO, APLICACION DE ASHFORD FORMULA PARA ACABADO PULIDO, MANO DE OBRA, MATERIAL, EQUIPO, Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETOMR | CONCRETO PROFESIONAL MR = 45 KG/CM2 MODULO DE RUPTURA, ESPECIAL PARA PAVIMENTOS CON RESISTENCIA A LA FLEXION, DE 15 CMS. DE ESPESOR | m3 | 0.192000 | $1,050.00 | $201.60 |
| ASHFORD FORMULA | ASHFORD FORMULA | lit | 0.235400 | $70.00 | $16.48 |
| MEMBRANA DE PARAF. | tela prs plicout | M2 | 0.300000 | $15.00 | $4.50 |
| CIMBRA METALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.002000 | $82.38 | $0.16 |
| AGUA | AGUA | M3 | 0.005000 | $40.00 | $0.20 |
| BOMBEO | BOMBEO | M3 | 0.135000 | $100.00 | $13.50 |
| Suma de Material | $236.44 | ||||
| Mano de Obra | |||||
| CUADRILLA-SAMS-04 | 1 ALBAÑIL + 5 PEONES | JOR | 0.025641 | $1,440.56 | $36.94 |
| Suma de Mano de Obra | $36.94 | ||||
| Equipo | |||||
| REGLA VIBRATORIA | REGLA VIBRATORIA | hora | 0.003571 | $15.48 | $0.06 |
| ALLANADORA MECANIC. | ALLANADORA MECANICA CON ASPAS | hora | 0.025000 | $124.91 | $3.12 |
| Suma de Equipo | $3.18 | ||||
| Concepto | |||||
| ACERC3 * | Acero de refuerzo en cimentación del No. 3, de Fy=4200 kg/cm2, incluye: materiales, pruebas de resistencia de acuerdo con especificaciones, acarreos, cortes, desperdicios, habilitado, amarres, mano de obra, equipo y herramienta (P.U.O.T.). | TON | 0.005570 | $12,913.78 | $71.93 |
| Suma de Concepto | $71.93 | ||||
| Costo Directo | $348.49 |