| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 540.24 * | RAMPAS PARA MINUSVALIDOS DE CONCRETO ARMADO SEGUN PROYECTO INCLUYE: MATERIALES, MANO DE OBRA, ACARREOS, EQUIPO Y HERRAMIENTA. | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | M3 | 0.040000 | $40.00 | $1.60 |
| CONC.PREMEZ.F-C=250 | Concreto Premezclado F'c=250 Kg/cm2 T.M.A. 3/4" revenimiento tiro directo | M3 | 0.157500 | $930.00 | $146.48 |
| DUELA ECONOMICA 3/4" | Duela Economica 3/4" x 3 1/2" x 8 1/4' | pt | 1.050000 | $6.20 | $6.51 |
| CLAVO CON CABEZA DE | Clavo con cabeza de 3" .004KG/PZA PROM. | kg | 0.080000 | $16.12 | $1.29 |
| DIESEL | diesel | Lt | 0.250000 | $4.90 | $1.23 |
| MALLA LAC 6X6-6/6 | Malla lac 6x6 - 6x6 | M2 | 1.311200 | $20.70 | $27.14 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.200000 | $10.12 | $2.02 |
| ENDURECEDOR MINERAL | ENDURECEDOR MINERAL | LT | 0.187500 | $25.00 | $4.69 |
| Suma de Material | $190.95 | ||||
| Mano de Obra | |||||
| CUADRILLA-SAMS-05 | 1 ALBAÑIL + 1 PEON | JOR | 0.600000 | $617.54 | $370.52 |
| Suma de Mano de Obra | $370.52 | ||||
| Costo Directo | $561.48 |