| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 540.11 * | TOPE DE CONCRETO DE 1.50 MTS DE ANCHO Y 10 CMS DE ALTURA ARMADO CON VARILLA No. 4 COMO ANCLAJE Y PARRILLA No.3 A CADA 20 CMS. CON CRONCRETO DE 200KG/CM2 | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC.PREMEZ.F-C=200 | Concreto Premezclado F'c=200 Kg/cm2AM 3/4" REV. 10 cm +- 2.5 cm | M3 | 0.020000 | $826.00 | $16.52 |
| ACE#4 | MAT. | ACERO DE | 3.200000 | $7.59 | $24.29 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.089000 | $12.30 | $1.09 |
| AGUA | AGUA | M3 | 0.010000 | $40.00 | $0.40 |
| Suma de Material | $42.30 | ||||
| Mano de Obra | |||||
| CUADRILLA-SAMS-05 | 1 ALBAÑIL + 1 PEON | JOR | 0.125000 | $605.22 | $75.65 |
| Suma de Mano de Obra | $75.65 | ||||
| Equipo | |||||
| TALADRO ROTOMARTILLO | TALADRO ROTOMARTILLO MCA. DWALT 5/8"-1/2" | HR | 0.500000 | $18.92 | $9.46 |
| Suma de Equipo | $9.46 | ||||
| Costo Directo | $127.42 |