| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.1 | LIMPIEZA, TRAZO Y NIVELACION DEL AREA DE TRABAJO. INCLUYE MATERIALES, MANO DE OBRA EQUIPO Y TODO LO NECESARIO PARA LA CORRECTA EJECUCION DE LOS TRABAJOS. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CALHIDRA | CALHIDRA EN SACO | ton | 0.000200 | $935.60 | $0.19 |
| CIMBRA03 | madera para estacas | PT | 0.045000 | $4.34 | $0.20 |
| PINTURA ESMALTE COME | PINTURA ESMALTE | LT | 0.001500 | $58.45 | $0.09 |
| Suma de Material | $0.47 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | CUAD. 1 topografo + 2 cadeneros | JOR | 0.000313 | $1,313.57 | $0.41 |
| CUAD OC 01 | CUAD. 1 PEON | JOR | 0.010000 | $241.73 | $2.42 |
| Suma de Mano de Obra | $2.83 | ||||
| Equipo | |||||
| AMAQUINARIA-10 | TRANSITO CON TRIPIE Y PLOMADA OPTICA | HR | 0.012500 | $11.41 | $0.14 |
| AMAQUINARIA-08 | NIVEL CON TRIPIE | HR | 0.008333 | $24.00 | $0.20 |
| Suma de Equipo | $0.34 | ||||
| Auxiliar | |||||
| CONCRETO F`C=100 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2 AGREGADO MAXIMO 3/4, ELABORADO CON CEMENTO CPO-30-RS | M3 | 0.000100 | $675.73 | $0.07 |
| Suma de Auxiliar | $0.07 | ||||
| Costo Directo | $3.71 |