| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| B).-- | N-CTR.CAR-1.04.002/03 SUB-BASES 贸 BASES POR UNIDAD DE OBRA TERMINADA b).-BASE COMPACTADA AL CIEN POR CIENTO ( 100 % ) | M3 |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| REG. BCO | REGALIA DE BANCO | M3 | 1.250000 | $3.50 | $4.38 |
| Suma de Material | $4.38 | ||||
| Equipo | |||||
| MOTOCOF. CAT14G | MOTOCONFORMADORA CAT140G D | HR | 0.011100 | $667.53 | $7.41 |
| COMPACTADOR | COMPACTADOR DE RODILLO LISO | HR | 0.012500 | $242.30 | $3.03 |
| CAMION PIPA 1OOOOLTS | CAMION PIPA DE 10000 LTS | HR | 0.012500 | $261.84 | $3.27 |
| CARGF CAT966C | CARGADOR FRONTAL | HR | 0.010000 | $573.26 | $5.73 |
| Suma de Equipo | $19.44 | ||||
| Auxiliar | |||||
| AGUA INCLUYE ACARR | AGUA INCLUYE ACARREO | M3 | 0.200000 | $51.08 | $10.22 |
| TARIFA 1ER KM | TARIFA 1ER KM | M3 | 1.250000 | $3.86 | $4.83 |
| TARIFA KM SUB AL 1ER | TARIFA KM SUBSECUENTES AL 1ER KM | M3-KM | 11.250000 | $2.88 | $32.40 |
| SUB-BASE | MATERIAL TRITURADO PARA SUB-BASE | M3 | 1.250000 | $33.53 | $41.91 |
| Suma de Auxiliar | $89.35 | ||||
| Costo Directo | $113.17 |