| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| B).- | N-CTR.CAR-1.01.009/00 TERRAPLENES POR UNIDAD DE OBRA TERMINADA B).-SUBRASANTE COMPACTADA AL CIEN POR CIENTO ( 100 % ) | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| REG. BCO | REGALIA DE BANCO | M3 | 1.250000 | $3.50 | $4.38 |
| Suma de Material | $4.38 | ||||
| Equipo | |||||
| MOTOCOF. CAT14G | MOTOCONFORMADORA CAT140G D | HR | 0.009000 | $667.53 | $6.01 |
| COMPACTADOR | COMPACTADOR DE RODILLO LISO | HR | 0.009000 | $242.30 | $2.18 |
| CAMION PIPA 1OOOOLTS | CAMION PIPA DE 10000 LTS | HR | 0.009000 | $261.84 | $2.36 |
| CARGF CAT966C | CARGADOR FRONTAL | HR | 0.012000 | $573.26 | $6.88 |
| Suma de Equipo | $17.42 | ||||
| Auxiliar | |||||
| AGUA INCLUYE ACARR | AGUA INCLUYE ACARREO | M3 | 0.150000 | $51.08 | $7.66 |
| TARIFA 1ER KM | TARIFA 1ER KM | M3 | 1.250000 | $3.86 | $4.83 |
| TARIFA KM SUB AL 1ER | TARIFA KM SUBSECUENTES AL 1ER KM | M3-KM | 2.250000 | $2.88 | $6.48 |
| Suma de Auxiliar | $18.97 | ||||
| Costo Directo | $40.77 |