| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 133 | PUENTE " " DE 40 X 239 CM. | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SV | SEÑAL SEÑALAMIENTO VERTICAL (E.P. 18) PUENTE DE 40 X 239 CM. | PZA | 1.000000 | $3,650.00 | $3,650.00 |
| Suma de Material | $3,650.00 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.250000 | $2,277.07 | $569.27 |
| Suma de Mano de Obra | $569.27 | ||||
| Auxiliar | |||||
| 03-2040 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.140000 | $921.59 | $129.02 |
| Suma de Auxiliar | $129.02 | ||||
| Costo Directo | $4,348.29 |