| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.6.1.1 | TRAZO Y NIVELACIÒN TOPOGRÀFICA DEL TERRENO, ESTABLECIENDO EJES DE REFERENCIAS Y BANCO DE NIVEL AUXILIARES, MOJONERAS. EL PRECIO UNITARIO INCLUYE: APARATOS TOPOGRAFICOS, TRÀNSITO, NIVEL, MOJONETAS, BANCOS DE NIVEL Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÒN. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 500165-3045 | Duela 3/4 x 4 x 8 | pt | 0.040670 | $18.50 | $0.75 |
| 130100-1205 | Polin 3 1/2 x3 1/2 x8 1/4 | pt | 0.068340 | $9.54 | $0.65 |
| 130100-1045 | Barrote 2"x4"x8 1/4 | pt | 0.052510 | $14.32 | $0.75 |
| 500180-1050 | Rekor c/reg.(esmalte alkidalico), marca Comex | L | 0.003810 | $48.52 | $0.18 |
| 103247-1265 | Hilo plastico | m | 0.395150 | $1.65 | $0.65 |
| 175125-2010 | Clavo c/cabeza de 2 -4 | kg | 0.003000 | $16.25 | $0.05 |
| 103100-1005 | Calhidra | Ton | 0.000640 | $1,324.00 | $0.85 |
| Suma de Material | $3.89 | ||||
| Mano de Obra | |||||
| A100105-4000 | Cuadrilla de topografÃa. Incluye : topógrafo, ayudante, cadenero, estadalero y herramienta. | Jor | 0.006990 | $2,080.89 | $14.55 |
| Suma de Mano de Obra | $14.55 | ||||
| Equipo | |||||
| C990180-1510 | Nivel topográfico basculante con precisión de +/- 2 mm/km nivelado aumentos del lente de 40 x imagen directa y tripie marca keuffel & esser co modelo dummpy. | h | 0.095000 | $0.56 | $0.05 |
| Suma de Equipo | $0.05 | ||||
| Costo Directo | $18.49 |