| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 20 | SUM. E INST. DE CASTILLO DE 15 X 15 CMS. A BASE DE CONCRETO F`C= 250 KG/CM2 REFORZADO CON 4 VRS. DE EL No. 3 Y ESTRIBOS No. 2 @20 CMS. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Concepto | |||||
| 230.10 | ACERO DE REFUERZO FY=4200 KG/CM2 VARIOS DIAMETROS EN CIMENTACION.INCLUYE: ACARREOS, TRASLAPES, GANCHOS, ALAMBRE DE AMARRE. | TN | 0.003000 | $13,955.05 | $41.87 |
| 230.9 | CIMBRA COMUN EN CIMENTACION A BASE DE MADERA DE PINO INCLUYE: CIMBRA, DECIMBRA, ACARREOS, DESMOLDANTE,DESPERDICIOS. | M2 | 0.500000 | $109.28 | $54.64 |
| C1 | SUMINISTRO Y COLOCACION DE CONCRETO fc=250 KG/CM2 INCLUYE:EQUIPO, MATERIAL, MANO DE OBRA, CURADO Y VIBRADO. | M3 | 0.040000 | $976.82 | $39.07 |
| Suma de Concepto | $135.58 | ||||
| Costo Directo | $135.58 |