| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 19. | Cimbra y Descimbra en muros. | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA-001 | CIMBRAPLAY 16 MM HOJA DE 1.22 X 2.44 | m2 | 0.250000 | $97.00 | $24.25 |
| CIMBRA-002 | MADERA DE PINO DE 3A. | pt | 3.500000 | $8.00 | $28.00 |
| CHAFLAN 1" | CHAFLAN 1" | ml | 1.100000 | $3.20 | $3.52 |
| CLAVO (VARIAS MED.) | CLAVO PARA MADERA VARIAS MEDIDAS | kg | 0.150000 | $18.00 | $2.70 |
| 0950-05 | DIESEL | lt | 0.450000 | $7.38 | $3.32 |
| ALAMBRE REC | ALAMBRE RECOCIDO CAL. 16 | kg | 0.036000 | $12.00 | $0.43 |
| Suma de Material | $62.22 | ||||
| Mano de Obra | |||||
| MO11 | CUADRILLA (1 CARPINTERO + 1 AYUDANTE) | jor | 0.090909 | $994.89 | $90.44 |
| Suma de Mano de Obra | $90.44 | ||||
| Equipo | |||||
| 03-4390 | CAMION PICK-UP FORD 1.5 TONELADAS MOTOR DE GASOLINA | Hora | 0.010000 | $126.72 | $1.27 |
| Suma de Equipo | $1.27 | ||||
| Costo Directo | $153.93 |