| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MN28 | Reparación de lavaderos, P.U.O.T. | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA EN PIPA | AGUA TRANSPORTADA EN PIPA | m3 | 0.025000 | $60.00 | $1.50 |
| 0127-05 | CIMBRA METALICA | m2 | 0.400000 | $27.20 | $10.88 |
| REG BANCO DESP | REGALIAS POR BANCO DE DESPERDICIOS. | m3 | 0.400000 | $6.00 | $2.40 |
| Suma de Material | $14.78 | ||||
| Mano de Obra | |||||
| CUAD 002-OC | CUAD 002-OC ( OFICIAL ALBANIL+PEON ) | jor | 0.116279 | $762.55 | $88.67 |
| Suma de Mano de Obra | $88.67 | ||||
| Equipo | |||||
| HIDRO KAR G2600VH | HIDROLAVADORA KARCHER G200VH MOTOR HONDA 5.5 HP | hora | 0.100000 | $116.80 | $11.68 |
| CAM RED 3.5 TON | CAMION DODGE 3.5 TON ESTACAS DE 230 HP | hora | 0.100000 | $282.71 | $28.27 |
| CAMION VOLTEO | CAMION DE VOLTEO FAMSA DE 7M3 MOTOR DIESEL 140 HP | hora | 0.050000 | $336.65 | $16.83 |
| COMP T250 | COMPRESOR INGRESOLL-RAND T250 250 CPM 105 HP | hora | 0.100000 | $270.38 | $27.04 |
| Suma de Equipo | $83.82 | ||||
| Auxiliar | |||||
| 03-2040 | CONCRETO F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.133000 | $966.92 | $128.60 |
| ELAB CONC OBRA | ELABORACION DE CONCRETO EN OBRA | m3 | 0.133000 | $239.39 | $31.84 |
| Suma de Auxiliar | $160.44 | ||||
| Costo Directo | $347.71 |