| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| MN27 | Reparaci贸n de cunetas y contracunetas, P.U.O.T. | M |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CELOTEX | CELOTEX | m2 | 0.100000 | $5.30 | $0.53 |
| PINT VINIM COMEX | PINTURA VINIMEX DE COMEX | litro | 0.200000 | $65.00 | $13.00 |
| AGUA EN PIPA | AGUA TRANSPORTADA EN PIPA | m3 | 0.025000 | $60.00 | $1.50 |
| DISCO DE DIAMANTE | DISCO DE DIAMANTE | pieza | 0.005000 | $1,600.00 | $8.00 |
| REG BANCO DESP | REGALIAS POR BANCO DE DESPERDICIOS. | m3 | 0.200000 | $6.00 | $1.20 |
| 2406-59 | CURAFEST BLANCO, MARCA FESTER. | LITRO | 0.166667 | $26.27 | $4.38 |
| DESMOLDANTE | DESMOLDANTE | litro | 0.100000 | $10.20 | $1.02 |
| 0127-05 | CIMBRA METALICA | m2 | 0.400000 | $27.20 | $10.88 |
| Suma de Material | $40.51 | ||||
| Mano de Obra | |||||
| CUAD 013-E | CUADRILLA 013-E ( 1 ALBA脩IL + 4 AYUDANTES ) | jor | 0.066667 | $1,863.53 | $124.24 |
| Suma de Mano de Obra | $124.24 | ||||
| Equipo | |||||
| CORTADORA DE CONCRET | CORTADORA DE CONCRETO TARGET EC 200 18 HP MOTOR DE GASOLINA | hora | 0.066667 | $107.94 | $7.20 |
| CAMION VOLTEO | CAMION DE VOLTEO FAMSA DE 7M3 MOTOR DIESEL 140 HP | hora | 0.025000 | $336.65 | $8.42 |
| CAM RED 3.5 TON | CAMION DODGE 3.5 TON ESTACAS DE 230 HP | hora | 0.016667 | $282.71 | $4.71 |
| Suma de Equipo | $20.32 | ||||
| Auxiliar | |||||
| ELAB CONC OBRA | ELABORACION DE CONCRETO EN OBRA | m3 | 0.200000 | $239.39 | $47.88 |
| 03-2040 | CONCRETO F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.200000 | $966.92 | $193.38 |
| Suma de Auxiliar | $241.26 | ||||
| Costo Directo | $426.33 |