| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| UA8006 | Limpieza de la superficie de rodamiento, P.U.O.T. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA EN PIPA | AGUA TRANSPORTADA EN PIPA | m3 | 0.002000 | $60.00 | $0.12 |
| ARENA PUST OBR | ARENA PUESTA EN OBRA | m3 | 0.000100 | $200.00 | $0.02 |
| Suma de Material | $0.14 | ||||
| Mano de Obra | |||||
| CUAD 4Y | CUADRILLA 4Y ( 4 AYUDANTES ) | jor | 0.002000 | $1,422.92 | $2.85 |
| Suma de Mano de Obra | $2.85 | ||||
| Equipo | |||||
| BARREDORA 70 HP | BARREDORA AUTOPROPULSADA BROCE-BROM 2.40 MT MOTOR 70 HP | hora | 0.000667 | $272.61 | $0.18 |
| COMP T250 | COMPRESOR INGRESOLL-RAND T250 250 CPM 105 HP | hora | 0.000667 | $270.38 | $0.18 |
| HIDRO KAR G2600VH | HIDROLAVADORA KARCHER G200VH MOTOR HONDA 5.5 HP | hora | 0.000667 | $116.80 | $0.08 |
| CAM RED 3.5 TON | CAMION DODGE 3.5 TON ESTACAS DE 230 HP | hora | 0.000667 | $282.71 | $0.19 |
| CAMION VOLTEO | CAMION DE VOLTEO FAMSA DE 7M3 MOTOR DIESEL 140 HP | hora | 0.000667 | $336.65 | $0.22 |
| Suma de Equipo | $0.85 | ||||
| Costo Directo | $3.84 |