| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MN47 | Limpieza de defensas y barreras centrales, P.U.O.T. | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA EN PIPA | AGUA TRANSPORTADA EN PIPA | m3 | 0.010000 | $60.00 | $0.60 |
| DETERGENTE | DETERGENTE | kg | 0.015000 | $15.30 | $0.23 |
| Suma de Material | $0.83 | ||||
| Mano de Obra | |||||
| CUAD 4Y | CUADRILLA 4Y ( 4 AYUDANTES ) | jor | 0.014286 | $1,422.92 | $20.33 |
| Suma de Mano de Obra | $20.33 | ||||
| Equipo | |||||
| COMP T250 | COMPRESOR INGRESOLL-RAND T250 250 CPM 105 HP | hora | 0.025000 | $270.38 | $6.76 |
| HIDRO KAR G2600VH | HIDROLAVADORA KARCHER G200VH MOTOR HONDA 5.5 HP | hora | 0.025000 | $116.80 | $2.92 |
| CAM RED 3.5 TON | CAMION DODGE 3.5 TON ESTACAS DE 230 HP | hora | 0.025000 | $282.71 | $7.07 |
| Suma de Equipo | $16.75 | ||||
| Costo Directo | $37.90 |