| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| UA8407 | Lavado de defensa metálica en P.I.V., P.U.O.T. | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA EN PIPA | AGUA TRANSPORTADA EN PIPA | m3 | 0.020000 | $60.00 | $1.20 |
| DESENGRASANTE | DESENGRASANTE | kg | 0.050000 | $17.90 | $0.90 |
| DETERGENTE | DETERGENTE | kg | 0.050000 | $15.30 | $0.77 |
| Suma de Material | $2.86 | ||||
| Mano de Obra | |||||
| CUAD 4Y | CUADRILLA 4Y ( 4 AYUDANTES ) | jor | 0.033333 | $1,422.92 | $47.43 |
| Suma de Mano de Obra | $47.43 | ||||
| Equipo | |||||
| COMP T250 | COMPRESOR INGRESOLL-RAND T250 250 CPM 105 HP | hora | 0.050000 | $270.38 | $13.52 |
| HIDRO KAR G2600VH | HIDROLAVADORA KARCHER G200VH MOTOR HONDA 5.5 HP | hora | 0.050000 | $116.80 | $5.84 |
| CAM RED 3.5 TON | CAMION DODGE 3.5 TON ESTACAS DE 230 HP | hora | 0.050000 | $282.71 | $14.14 |
| Suma de Equipo | $33.49 | ||||
| Costo Directo | $83.78 |