| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MEL643. | TABLERO AP TIPO BT41M24/12S 220/127V 3F 4H MCA.BTICINO CON INT.PPAL DE 3PX40A Y LOS SIGUIENTES INT.DERIVADOS: 1PX15A 8P 1PX20A 2P | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TAB BT41M63-125/12E | TAB BT41M100/12E CON INT PRINCIPAL REQUERIDO | PZA | 1.000000 | $3,234.30 | $3,234.30 |
| INT TERM BTN1/15 | INT TERM BTN1/15 | PZA | 8.000000 | $31.04 | $248.32 |
| INT TERM BTN1/20 | INT TERM BTN1/20 | PZA | 2.000000 | $31.04 | $62.08 |
| TAQUETE SCI 3/8" | TAQUETE TIPO SCI DE 3/8" CLEVIS | PZA | 4.000000 | $3.69 | $14.76 |
| BROCA P/CONCRETO 3/8 | BROCA PARA CONCRETO DE 5/8" DE DIAMETRO X 6" DE LONGITUD Y 3/8" DE ZANCO | PZA | 0.090000 | $38.41 | $3.46 |
| TORNILLO 3/8" | TORNILLO 3/8" | PZA | 4.000000 | $2.72 | $10.88 |
| Suma de Material | $3,573.80 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 1.000000 | $717.17 | $717.17 |
| Suma de Mano de Obra | $717.17 | ||||
| Costo Directo | $4,290.97 |