| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MEL516 | TABLERO "AUR4" TIPO 220/127V 3F 4H MCA.CON INT.PPAL DE 3PX100A Y LOS SIGUIENTES INT.DERIVADOS: 1PX15A 3PZA 1PX20A 2PZA 3PX70A 1PZA | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TAB BT41M63-125/12E | TAB BT41M100/12E CON INT PRINCIPAL REQUERIDO | PZA | 1.000000 | $3,234.30 | $3,234.30 |
| INT TERM BTN1/15 | INT TERM BTN1/15 | PZA | 3.000000 | $31.04 | $93.12 |
| INT TERM BTN1/20 | INT TERM BTN1/20 | PZA | 2.000000 | $31.04 | $62.08 |
| INT TERM BTN3/70 | INT TERM BTN3/70 | PZA | 1.000000 | $237.65 | $237.65 |
| TABLERO AUR4 | TABLERO "AUR4" TIPO 220/127V 3F 4H MCA.CON INT.PPAL DE 3PX100A Y LOS SIGUIENTES INT.DERIVADOS: 1PX15A 3PZA 1PX20A 2PZA 3PX70A 1PZA | PZA | 1.000000 | $3,826.36 | $3,826.36 |
| Suma de Material | $7,453.51 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.500000 | $717.17 | $358.59 |
| CUADRILLA NO. 09 | Cuadrilla albañileria | jor | 0.500000 | $638.63 | $319.32 |
| Suma de Mano de Obra | $677.90 | ||||
| Costo Directo | $8,131.41 |