| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MEM223 | COND.REC.C/TAPA Y EMPAQ. FSC-2 19MM | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| COND REC FSC2 19 MM | COND.REC.C/TAPA Y EMPAQ. FSC-2 19MM | PZA | 1.000000 | $66.78 | $66.78 |
| TAQUETE SCI 3/8" | TAQUETE TIPO SCI DE 3/8" CLEVIS | PZA | 2.000000 | $3.69 | $7.38 |
| TORNILLO 3/8" | TORNILLO 3/8" | PZA | 2.000000 | $2.72 | $5.44 |
| Suma de Material | $79.60 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.028571 | $717.17 | $20.49 |
| Suma de Mano de Obra | $20.49 | ||||
| Costo Directo | $100.09 |