| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MEI611 | SOPORTE TRAPECIO COLGANTE PARA TUBO CON VARILLA Y UNICANAL DE 1.10M DE LONG | P |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BROCA P/CONCRETO 3/8 | BROCA PARA CONCRETO DE 5/8" DE DIAMETRO X 6" DE LONGITUD Y 3/8" DE ZANCO | PZA | 0.030000 | $38.41 | $1.15 |
| TAQUETE SCI 3/8" | TAQUETE TIPO SCI DE 3/8" CLEVIS | PZA | 2.000000 | $3.69 | $7.38 |
| TRAPECIO CLEVIS 3/8" | TRAPECIO CLEVIS 3/8" | PZA | 2.000000 | $8.05 | $16.10 |
| VARILLA ROSC. 3/8 | VARILLA ROSCADA DE 3/8" | ML | 2.000000 | $10.95 | $21.90 |
| TUERCA GALV. 3/8" | TUERCA GALV. 3/8" | PZA | 4.000000 | $0.36 | $1.44 |
| ROLDANA DE 3/8" | ROLDANA DE 3/8" | PZA | 4.000000 | $0.19 | $0.76 |
| UNICANAL U-10 | UNICANAL U-10 | ML | 1.100000 | $11.57 | $12.73 |
| Suma de Material | $61.46 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.040000 | $717.17 | $28.69 |
| Suma de Mano de Obra | $28.69 | ||||
| Auxiliar | |||||
| ANDAMIO | MODULO DE 1.55 MTS PARA INSTALACIONES | R/D | 0.025000 | $28.92 | $0.72 |
| Suma de Auxiliar | $0.72 | ||||
| Costo Directo | $90.87 |