| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MEI051 | SOPORTE SOBRE MURO O LOSA PARA TUBO CON UNICANAL DE 3.00M DE LONGITUD | P |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PIJA NO 8 X 1 1/4" | PIJA NO 8 X 1 1/4" | PZA | 3.000000 | $0.10 | $0.30 |
| TAQUETE DE PLAST 3/8 | TAQUETE 3/8 PLASTICO | PZA | 3.000000 | $0.63 | $1.89 |
| BROCA P/CONCRETO 3/8 | BROCA PARA CONCRETO DE 5/8" DE DIAMETRO X 6" DE LONGITUD Y 3/8" DE ZANCO | PZA | 0.030000 | $38.41 | $1.15 |
| UNICANAL U-10 | UNICANAL U-10 | ML | 3.020000 | $11.57 | $34.94 |
| Suma de Material | $38.28 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.050000 | $717.17 | $35.86 |
| Suma de Mano de Obra | $35.86 | ||||
| Auxiliar | |||||
| ANDAMIO | MODULO DE 1.55 MTS PARA INSTALACIONES | R/D | 0.016900 | $28.92 | $0.49 |
| Suma de Auxiliar | $0.49 | ||||
| Costo Directo | $74.63 |