| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MEL401 | TABLERO CMI TIPO 480/277V 3F 4H SQUARE´D CON INT.PPAL DE 3PX70A Y LOS SIGUIENTES INT.DERIVADOS: 3PX15A 2PZA 3PX20A 1PZA 3PX70A 1PZA | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TABLERO CMI | TABLERO CMI TIPO NF 124 AB02-S 480/277V 3F 4H SQUARE´D CON INT.PPAL DE 3PX100A Y LOS SIGUIENTES INT.DERIVADOS: 3PX15A 2PZA 3PX20A 1PZA 3PX70A 1PZA | PZA | 1.000000 | $8,854.16 | $8,854.16 |
| TAQUETE SCI 3/8" | TAQUETE TIPO SCI DE 3/8" CLEVIS | PZA | 4.000000 | $3.69 | $14.76 |
| BROCA P/CONCRETO 3/8 | BROCA PARA CONCRETO DE 5/8" DE DIAMETRO X 6" DE LONGITUD Y 3/8" DE ZANCO | PZA | 0.050000 | $38.41 | $1.92 |
| VARILLA ROSC. 3/8 | VARILLA ROSCADA DE 3/8" | ML | 0.500000 | $10.95 | $5.48 |
| TUERCA GALV. 3/8" | TUERCA GALV. 3/8" | PZA | 4.000000 | $0.36 | $1.44 |
| Suma de Material | $8,877.76 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.600000 | $717.17 | $430.30 |
| Suma de Mano de Obra | $430.30 | ||||
| Auxiliar | |||||
| ANDAMIO | MODULO DE 1.55 MTS PARA INSTALACIONES | R/D | 0.333330 | $28.92 | $9.64 |
| Suma de Auxiliar | $9.64 | ||||
| Costo Directo | $9,317.70 |