| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 30 | IDEM ANTERIOR DE 25 X 19 MM DE d. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| RED-B-25X19 CU | RED-B-25X19 CU | PZA | 1.000000 | $8.00 | $8.00 |
| SOLDADURA 50X50 | SOLDADURA 50X50 | PZA | 0.023260 | $42.00 | $0.98 |
| PASTA FUNDENTE SILER | PASTA FUNDENTE SILER | PZA | 0.020000 | $35.00 | $0.70 |
| GAS BUTANO | GAS BUTANO | KG | 0.012750 | $7.50 | $0.10 |
| ESTOPA | ESTOPA | Kg. | 0.025000 | $13.00 | $0.33 |
| LIJA FINA ESMERIL | LIJA FINA ESMERIL | PZA | 0.050000 | $6.50 | $0.33 |
| Suma de Material | $10.42 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 32 IN | Cuadrilla de Plomeros | jor | 0.028571 | $811.29 | $23.18 |
| Suma de Mano de Obra | $23.18 | ||||
| Costo Directo | $33.60 |