| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 9.4 | POZO DE VISITA CONICO DE 0.60 A 1.20 MT. DE DIAMETRO Y 2.08 MT. DE PROFUNDIDAD. INCLUYE: EXCAVACION, AFINE DE FONDO, PLANTILLA DE CONCRETO SIMPLE F'C=150 KG/CM2. DE 15 CM. ESP.,MURO DE TABIQUE 26 CM. ESP. ASENTADO C/MORTERO CEM-ARENA 1:5, APLANADO CON MORTERO CEM-ARENA 1:3 ( INCLUYE CEMENTO IMPERMEABLE EN LA ELABORACION ), CON ESPESOR MINIMO DE 1 CM, MEDIA CAÑA CON TABIQUE Y ESCALONES DE 3/4"........................ ... | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TABIQUE | TABIQUE ROJO | PZA | 916.720000 | $1.15 | $1,054.23 |
| REDONDO LISO | REDONDO LISO | kg | 29.850000 | $9.80 | $292.53 |
| TUBO PARA CAÑA | TUBO PARA MEDIA CAÑA | PZA | 1.000000 | $55.00 | $55.00 |
| Suma de Material | $1,401.76 | ||||
| Mano de Obra | |||||
| CUAD OC 07 | CUAD. 2 PEONES | JOR | 2.250000 | $482.94 | $1,086.62 |
| Suma de Mano de Obra | $1,086.62 | ||||
| Auxiliar | |||||
| MORTERO 1:5 | MORTERO CEMENTO ARENA 1:5 PARA EL JUNTEO DE TABIQUE | M3 | 1.067000 | $657.37 | $701.41 |
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.380000 | $944.48 | $358.90 |
| APLANADO FINO | APLANADO FINO | M2 | 5.940000 | $93.95 | $558.06 |
| AUX-15 | CIMBRA COMUN DE MADERA INCLUYE: SUMINISTRO DE MATERIALES, HABILITADO, SEPRADORES, LUBRICANTES, DESCIMBRADO, EQUIPO, HERRAMIENTA, MANO DE OBRA, RAHABILITADO, PARA SU REUSO, (CINCO USOS) Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | M2 | 2.130000 | $77.98 | $166.10 |
| REPELLADO EN MURO EX | REPELLADO EN MURO EXTERIOR DE 1 CM. CON CEMENTO IMPERMEABLE | m2 | 9.920000 | $80.07 | $794.29 |
| Suma de Auxiliar | $2,578.77 | ||||
| Concepto | |||||
| PLA-001 | PLANTILLA DE CONCRETO F´C=100 KG/CM2 HECHO EN OBRA DE 5 CM DE ESPESOR, INCLUYE COMPACTACION DE FONDO, AFINE DE CEPAS SUMINISTROS, FABRICACION Y VACIADO DE CONCRETO. | M2 | 2.540000 | $61.03 | $155.02 |
| CE-03-03 | ACERO DE REFUERZO DEL No. 3 | ton | 0.007000 | $12,224.42 | $85.57 |
| 7.2 | EXCAVACION CON MAQUINA EN CEPAS DE 0.00 A 2.00 MTS DE PROFUNDIDAD, EN MATERIAL A Y/O "B", TRABAJO EJECUTADO CON MEDIOS MECANICOS, INCLUYE: DEPOSITO DE MATERIAL A UN COSTADO DE LA CEPA. | M3 | 15.460000 | $20.74 | $320.64 |
| 7.3 | AFINE MANUAL EN FONDO DE CEPAS C/MAQ. EN MATERIAL "A" EN SECO | M2 | 2.540000 | $6.18 | $15.70 |
| 7.8 | RELLENO CON EQUIPO MANUAL CON MATERIAL PRODUCTO DE EXCAVACION , INCLUYE: SELECCION Y VOLTEO CON PALA DE MANO COMPACTADO CON APISONADOR VIBRATORIO ADICIONANDOLE HUMEDAD EN CAPAS DE 20 CMS. DE ESPESOR AL 90% PRUEBA PROCTOR STANDAR, O LO INDICADO EN PLANOS....... ... | M3 | 10.850000 | $50.97 | $553.02 |
| 7.5 | CARGA Y ACARREO EN CAMION VOLTEO DE MATERIAL SOBRANTE DE EXCAVACION. 1ER. KILOMETRO. | M3 | 5.990000 | $12.12 | $72.60 |
| Suma de Concepto | $1,202.55 | ||||
| Costo Directo | $6,269.69 |