| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HID-102 | TUBO DE PVC HIDRAULICO ANGER RD-32.5 DE 4" | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO PVC HID 4X | TUBO DE PVC HIDRAULICO ANGER RD 32.5 DE 4" DE DIAMETRO. | ML | 1.030000 | $59.00 | $60.77 |
| CEMENTO WELD ON 721X | Cemento Weld On para alta presion bote 500 ml | PZA | 0.046500 | $62.37 | $2.90 |
| Suma de Material | $63.67 | ||||
| Mano de Obra | |||||
| CUAD OC 12 | (1 Of. Albanil + 1 Peón) | JOR | 0.017379 | $687.10 | $11.94 |
| Suma de Mano de Obra | $11.94 | ||||
| Concepto | |||||
| 7.2 | EXCAVACION CON MAQUINA EN CEPAS DE 0.00 A 2.00 MTS DE PROFUNDIDAD, EN MATERIAL A Y/O "B", TRABAJO EJECUTADO CON MEDIOS MECANICOS, INCLUYE: DEPOSITO DE MATERIAL A UN COSTADO DE LA CEPA. | M3 | 0.560000 | $20.74 | $11.61 |
| 7.8 | RELLENO CON EQUIPO MANUAL CON MATERIAL PRODUCTO DE EXCAVACION , INCLUYE: SELECCION Y VOLTEO CON PALA DE MANO COMPACTADO CON APISONADOR VIBRATORIO ADICIONANDOLE HUMEDAD EN CAPAS DE 20 CMS. DE ESPESOR AL 90% PRUEBA PROCTOR STANDAR, O LO INDICADO EN PLANOS....... ... | M3 | 0.550000 | $50.97 | $28.03 |
| Suma de Concepto | $39.65 | ||||
| Costo Directo | $115.26 |