| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| S-1.16 | R1- de 60X0.60 | Pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BLOC NO 6 | BLOC NO 6 | m2 | 3.200000 | $78.40 | $250.88 |
| CONCRETO PRE-04 | CONCRETO PREMEZCLADO DE F'C= 200 KG/CM2 | M3 | 0.250000 | $617.40 | $154.35 |
| CIMBRA-01 | CIMBRAPLAY | M2 | 1.400000 | $80.36 | $112.50 |
| CIMBRA-02 | CLAVO | Kg. | 1.500000 | $11.76 | $17.64 |
| ACERO-01 | ACERO DEL # 3 ( 1/2") AL # 6 (3/4) | KG | 12.000000 | $5.88 | $70.56 |
| MARCO Y CONTRAMARCO | MARCO Y CONTRAMARCO | pza | 1.000000 | $425.00 | $425.00 |
| Suma de Material | $1,030.93 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | jor | 1.200000 | $609.09 | $730.91 |
| Suma de Mano de Obra | $730.91 | ||||
| Equipo | |||||
| MAQUINARIA-12 | RETROEXCAVADORA CARGADORA MODELO 416 D ACCIONADA POR MOTOR DIESEL DE INYECCION DIRECTA , MODELO 3054T DE 4 CILINDROS. CON UNA POTENCIA DE 75 HP. | HR | 0.500000 | $130.93 | $65.47 |
| Suma de Equipo | $65.47 | ||||
| Auxiliar | |||||
| CONCTO F-C=100 | Concreto f'c=100 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3 | 0.100000 | $677.33 | $67.73 |
| Suma de Auxiliar | $67.73 | ||||
| Costo Directo | $1,895.04 |