| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 5004.36 | PINTURA A TUBERIA DE 100 MM DE Ø SEGUN CODIGO O NORMA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PINTURA SHERWIN | PINTURA SHERWIN | LT | 0.160000 | $64.02 | $10.24 |
| CROMATO ZINC | CROMATO ZINC | LTS | 0.150000 | $72.75 | $10.91 |
| THINER | THINER | LT | 0.300000 | $17.00 | $5.10 |
| ESTOPA | ESTOPA | Kg. | 0.013000 | $18.00 | $0.23 |
| Suma de Material | $26.49 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 21 | (1 Of. Pintor + 1 Ayudante) | jor | 0.020000 | $701.13 | $14.02 |
| Suma de Mano de Obra | $14.02 | ||||
| Costo Directo | $40.51 |