| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 5004.35 | PINTURA A TUBERIA DE 75 MM DE Ø SEGUN CODIGO O NORMA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PINTURA SHERWIN | PINTURA SHERWIN | LT | 0.120000 | $64.02 | $7.68 |
| CROMATO ZINC | CROMATO ZINC | LTS | 0.025000 | $72.75 | $1.82 |
| THINER | THINER | LT | 0.034000 | $17.00 | $0.58 |
| ESTOPA | ESTOPA | Kg. | 0.013000 | $18.00 | $0.23 |
| Suma de Material | $10.31 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 21 | (1 Of. Pintor + 1 Ayudante) | jor | 0.020000 | $701.13 | $14.02 |
| Suma de Mano de Obra | $14.02 | ||||
| Costo Directo | $24.34 |