| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 5000.357 | PINTURA A TUBERIA DE 64 MM DE Ø SEGUN CODIGO O NORMA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PINTURA SHERWIN | PINTURA SHERWIN | LT | 0.100000 | $64.02 | $6.40 |
| CROMATO ZINC | CROMATO ZINC | LTS | 0.025000 | $72.75 | $1.82 |
| THINER | THINER | LT | 0.034000 | $17.00 | $0.58 |
| ESTOPA | ESTOPA | Kg. | 0.013000 | $18.00 | $0.23 |
| Suma de Material | $9.03 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 21 | (1 Of. Pintor + 1 Ayudante) | jor | 0.016667 | $701.13 | $11.69 |
| Suma de Mano de Obra | $11.69 | ||||
| Costo Directo | $20.72 |