| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CMC-031 | ESCALERAS MARINAS PARA ACCESO CELDAS DE CISTERNA DE 0.60 X 3.00 M, LADO INTERNO, ESCALERA DE ALUMINIO, INCLUYE: CORTES, BISELADO, SOLDADURAS, ESMERILADO, ACCESORIOS, FIJACION, SUMINISTRO Y ACARREO DE MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO, P.U.O.T. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SOLDA | SOLDADURA E-6013 DE 1/8" | KG | 0.600000 | $65.00 | $39.00 |
| GAS A | GAS ACETILENO | KG | 0.900000 | $82.00 | $73.80 |
| GAS O | GAS OXIGENO | M3 | 2.700000 | $25.00 | $67.50 |
| TUBO NEGRO 2" C40 | 5.48 kg/ml | kg | 65.000000 | $14.00 | $910.00 |
| ESMALTE | esmalte | lt | 0.600000 | $55.00 | $33.00 |
| THINER | thiner | lt | 0.450000 | $15.00 | $6.75 |
| Suma de Material | $1,130.05 | ||||
| Mano de Obra | |||||
| CUAD OC 22 | CUAD. 22 1 HOJALTERO/HERRERO + 1 AYTE. | jor | 2.000000 | $994.17 | $1,988.34 |
| CUAD OC 08 | CUAD. 1 PINTOR + 1 AYTE | JOR | 0.083333 | $1,105.17 | $92.10 |
| Suma de Mano de Obra | $2,080.44 | ||||
| Equipo | |||||
| 03-0006 | SOLDADOR DE ARCO ELECTRICO | HR | 1.200000 | $57.45 | $68.94 |
| AMAQUINARIA-01 | EQUIPO DE CORTE OXIGENO-GAS | HR | 1.500000 | $11.45 | $17.18 |
| 03-0005 | PULIDORA | HR | 3.000000 | $2.29 | $6.87 |
| Suma de Equipo | $92.99 | ||||
| Costo Directo | $3,303.47 |