| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HERR-016 | BASTIDOR DE PTR 2"x2" SOBRE BARRA DE LOUNGE. EL PRECIO UNITARIO INCLUYE: SUMINISTRO Y ACARREO DE LOS MATERIALES, TRAZO, NIVELACION, HABILITADO, MONTAJE, CORTES, SOLDADURA, FIJACION, PREPARACION DE LA SUPERFICIE, APLICACION DE PINTURA ANTICORROSIVA, MANIOBRAS, LIMPIEZA DEL AREA, ANDAMIOS, MANO DE OBRA, HERRAMIENTA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA EJCUCION. P.U.O.T. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SOLDA | SOLDADURA E-6013 DE 1/8" | KG | 0.020000 | $65.00 | $1.30 |
| GAS A | GAS ACETILENO | KG | 0.150000 | $82.00 | $12.30 |
| GAS O | GAS OXIGENO | M3 | 0.500000 | $25.00 | $12.50 |
| TUBO NEGRO 2" C40 | 5.48 kg/ml | kg | 6.000000 | $14.00 | $84.00 |
| ESMALTE | esmalte | lt | 0.050000 | $55.00 | $2.75 |
| THINER | thiner | lt | 0.030000 | $15.00 | $0.45 |
| PTR 2" | CAL 12 DE 4.17 KG/ML | KG | 12.510000 | $10.00 | $125.10 |
| Suma de Material | $238.40 | ||||
| Mano de Obra | |||||
| CUAD OC 22 | CUAD. 22 1 HOJALTERO/HERRERO + 1 AYTE. | jor | 0.055556 | $994.17 | $55.23 |
| CUAD OC 08 | CUAD. 1 PINTOR + 1 AYTE | JOR | 0.083333 | $1,105.17 | $92.10 |
| Suma de Mano de Obra | $147.33 | ||||
| Herramienta | |||||
| MALACATE | elevacion de materiales utilizando malacate con bogue incluye instalacion, operacion, etc. | (%)m | 0.110000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| 03-0006 | SOLDADOR DE ARCO ELECTRICO | HR | 0.400000 | $57.45 | $22.98 |
| AMAQUINARIA-01 | EQUIPO DE CORTE OXIGENO-GAS | HR | 0.500000 | $11.45 | $5.73 |
| 03-0005 | PULIDORA | HR | 0.100000 | $2.29 | $0.23 |
| Suma de Equipo | $28.93 | ||||
| Costo Directo | $414.66 |