| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALUM-H01 | SUMINISTRO Y COLOCACION DE VENTANA DE PROYECCION DE 1.00*.95 INCLUYE TODO SUS ACCESORIOS PARA SU BUEN FUNCIONAMIENTO CANCEL TIPO H-01 | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| VA011NAT | CONTRA MARCO VENT. PROYECC. NAT. | TMO | 0.695160 | $141.20 | $98.16 |
| B3-001NAT | CANAL BOLSA 3" NAT. | tmo | 3.576430 | $180.00 | $643.76 |
| B3-005NAT | TAPA BOLSA 3" NAT. | tmo | 2.635260 | $103.05 | $271.56 |
| B3-003NAT | ESCALONADO 3" NAT. | tmo | 2.352910 | $163.30 | $384.23 |
| B3-004NAT | JUNQUILLO PARA ESC. 3" NAT. | tmo | 2.352910 | $52.87 | $124.40 |
| TOR-3 | TORNILLO DE 3 X 10 | pza | 28.234920 | $0.45 | $12.71 |
| TAQPLAS | TAQUETE DE PLASTICO 1/4" | pza | 28.234920 | $0.18 | $5.08 |
| PIJA1X10 | PIJA 1 X 10 | pza | 33.881920 | $0.25 | $8.47 |
| AN-005 | ANGULO 1.5" X 1/8" X 3.66 MTS. NAT. | tmo | 0.065880 | $82.78 | $5.45 |
| PIJA2X10 | PIJA 2 X 10 | pza | 15.058630 | $0.75 | $11.29 |
| SELLACRI | SELLADOR ACRILICO | pza | 1.552920 | $11.60 | $18.01 |
| VA010NAT | MARCO VENT. PROYECC. NAT. | TMO | 0.695160 | $169.23 | $117.64 |
| VA012NAT | JUNQUILLO VENT. PROYECC. NAT. | TMO | 0.695160 | $67.59 | $46.99 |
| TOR-3 | TORNILLO DE 3 X 10 | pza | 7.415060 | $0.45 | $3.34 |
| TAQPLAS | TAQUETE DE PLASTICO 1/4" | pza | 9.268830 | $0.18 | $1.67 |
| PIJA1X10 | PIJA 1 X 10 | pza | 14.830120 | $0.25 | $3.71 |
| AN-005 | ANGULO 1.5" X 1/8" X 3.66 MTS. NAT. | tmo | 0.037080 | $82.78 | $3.07 |
| FELGRIS | FELPA GRIS | m | 7.415060 | $0.75 | $5.56 |
| JALPROY | JALADERA. | PZA | 0.926880 | $16.00 | $14.83 |
| BRAPROY | BRAZO P/VENT. PROYECC. 16" | JGO | 0.926880 | $47.35 | $43.89 |
| SELLACRI | SELLADOR ACRILICO | pza | 0.463440 | $11.60 | $5.38 |
| Suma de Material | $1,829.19 | ||||
| Mano de Obra | |||||
| JOGP041 | Cuadrilla de alumineros. Incluye : aluminero, ayudante y herramienta. | jor | 3.235580 | $456.21 | $1,476.10 |
| JOGP041 | Cuadrilla de alumineros. Incluye : aluminero, ayudante y herramienta. | jor | 1.000000 | $456.21 | $456.21 |
| Suma de Mano de Obra | $1,932.31 | ||||
| Costo Directo | $3,761.50 |