| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-05 | FABRICACIÓN DE ZAPATAS AISLADA 0.90 X 0.90 MTS. X 0.30 MTS., CON CONCRETO HECHO EN OBRA DE RESISTENCIA DE F¨C=250KG/CM2, REVENIMIENTO DE 10-12 CMS., AGREGADO MÁXIMO DE 3/4", ARMADAS CON VARILLAS DEL #4 @ 15 CMS. EN AMBOS SENTIDOS. INC.: MATERIAL | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.890000 | $868.90 | $773.32 |
| ACERO 03 | ACERO DEL # 3 AL 6 | KG | 13.970000 | $7.40 | $103.38 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.200000 | $7.00 | $8.40 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $10.00 | $1.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.270000 | $84.00 | $22.68 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.200000 | $10.00 | $2.00 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.010000 | $10.00 | $0.10 |
| Suma de Material | $910.88 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.800000 | $386.01 | $308.81 |
| CUADRILLA NO. 01 | (1 peón). | Jor | 0.200000 | $157.11 | $31.42 |
| Suma de Mano de Obra | $340.23 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.500000 | $15.40 | $7.70 |
| Suma de Equipo | $7.70 | ||||
| Costo Directo | $1,258.81 |